You are currently viewing Structural Steel Bridge Fabrication Procedure in India: Shop Drawing to Erection
Structural Steel Bridge Fabrication

The structural steel bridge fabrication procedure in India is one long chain, running from approved drawings to a girder resting on its bearings. Most site troubles, like a hole group 1 mm out or camber read on a sun-warmed girder, are born in the shop.

Here’s the quiet rule. Every stage below ends at a hold point. A steel bridge that skips one keeps the fault and carries it to the site, where fixes happen at height.

Structural Steel Bridge Fabrication Procedure in 10 Stages

Ten stages, ten gates, and each one stays shut until its check is signed.

StageHold point before the next
1. Shop drawingsQAP approved
2. Template layoutCamber layout checked
3. MaterialSteel cleared
4. CuttingEdge hardness checked
5. DrillingHole size and position
6. WeldingQualified WPS
7. NDTWelds accepted
8. Trial assemblyWithin tolerance
9. Surface protectionCoating thickness
10. ErectionBolt checks

Codes for Structural Steel Bridge Fabrication

Railway Girders

Railway work answers to IRS B1-2001 and the IRS Welded Bridge Code. RDSO’s BS-110 (R), revised in March 2016, adds checklists for before, during, and after fabrication.

Road Bridges

Road bridges follow IRC 24, with IRC:SP:104-2015 covering fabrication and erection. Most numbers below come straight from it.

Shop Drawings Approval

Nothing gets cut on a hunch. The shop works only from drawings the Engineer has approved (IRC:SP:104, cl. 1.1), and no work starts until the QAP is approved (cl. 1.5). Shop drawings approval is where the structural steel bridge fabrication procedure earns its calm.

Full-Scale Camber Layout

Camber is drawn full size on a leveled bed, and jigs are made from it (cl. 1.7). Railway work uses a calibrated steel tape (BS-110). Now the hidden detail. Camber is measured only after welding and cooling are complete (cl. 1.16.20). A warm girder fibs.

Material Test Certificates

Steel shows up with paperwork. Every section needs material test certificates, and test pieces from each cast go to an independent test house. Plates enter a steel bridge only when the MTC and that report agree (IRC:SP:104, cl. 1.3).

Grade and Quality

Railway girders use IS 2062 E250, quality B0, where service temperature stays at or above 0°C. Sub-zero areas get quality C, with toughness proven at -20°C. Plates under 12 mm skip normalizing (IRS B1, A&C slip No. 05).

Plates Tested First

UT is mandatory for plates 25 mm and thicker (cl. 1.16.2).

Cutting and Edge Preparation

A flame cut looks clean. It isn’t. The heat hardens the edge, and fatigue cracks love to start in that band. So cutting and edge preparation get their own gate in structural steel bridge fabrication.

Flame-Cut Edges

Hardness is capped at 350 BHN, and at least 2 mm comes off (cl. 1.9.1).

Holes and Drilling

Per cl. 1.11:

CaseRule
Fastener up to 25 mmHole 1.5 mm larger
Fastener above 25 mmHole 2.0 mm larger
E250 over 20 mm, E350 over 16 mmDrill 3 mm under, ream after assembly

Welding to an Approved WPS

A WPS is a recipe cooked once before anyone trusts it. The shop proves it on a test joint, and then production stays within those settings. That’s the least glamorous step in the structural steel bridge fabrication procedure in India.

Procedure and Welders

Procedures qualify to IS 7307 (Part 1); welders to IS 7310 (Part 1). Railway electrodes come from the RDSO list under IRS M-28.

Parameter Limits

Current ±10%, arc voltage ±7%, travel speed ±15% (cl. 1.15.10). Past that, stop.

Preheat by Thickness

Low-hydrogen or SAW on mild and medium tensile steel (Table 2):

Thickest partMinimum preheat
Up to 19 mmNone
19-38 mm10°C
38-64 mm66°C
Over 64 mm107°C

Ultrasonic Testing and NDT

Every weld gets a visual check, no exceptions. MPI and DPT catch cracks sitting on the surface. UT and RT hunt the buried ones, the kind that hide inside a steel bridge until traffic finds them.

Which Welds Get Tested

The amount of testing follows the stress (cl. 1.16.16):

Butt weld locationNDT extent
Tension flange, transverse100%
Tension flange, longitudinal10% of the length
Compression flange5% of length

Trial Assembly and Match Marking

Before anything ships, the neighbors meet. In trial assembly, modules are matched to the pieces beside them (IRC:SP:104, cl. 1.4), and railway work gets one complete span checked by RDSO (BS-110). It’s the last calm spot in the structural steel bridge fabrication procedure to catch a mismatch.

Tolerances That Matter

Appendix B sets the limits:

CheckTolerance
Overall girder length+6 / -3 mm
Bearing centers±1 mm
End diagonals±3 mm
Holes within a group±0.5 mm

Marking for Site

For match marking, each part carries a mark and serial number, stacked with marks visible (cl. 2.2.1).

Shot Blasting and Metallizing

No coating touches steel until fabrication is cleared. Then a clock starts. Shot blasting leaves a clean, rough surface that begins to rust within hours, so the spray follows fast. This part of structural steel bridge fabrication determines how long before anyone climbs up with a brush.

Metallizing Figures

Blast to Sa 2½ (cl. 1.18.2). Spray within 8 hours. Lay at least 2 passes for a nominal 150 µm, with no spot under 110 µm (Appendix E).

Zinc or Aluminum

Indian bridge specifications are written around sprayed aluminum. Zinc metallizing comes in when the contract names it, and its sacrificial action suits rail bridges exposed to collision damage.

Launching and Erection

The site picks the method. Never the reverse. Temporary works get checked before the first lift, because the structural steel bridge fabrication procedure either finishes cleanly or stumbles at launching and erection.

Choosing the Method

  • Crane lift: short, reachable spans.
  • Launching with a nose: over live roads, rail lines, or valleys.
  • Cantilever: long trusses with no ground support.
  • Float-in: rivers.

Site Checks

In multi-crane lifts, no crane reaches 75% of net capacity (Appendix K). Torque-check 10% of HSFG bolts per connection, minimum two (cl. 1.16.7).

SteelWorks: Your Steel Bridge Partner

SteelWorks is the one-call for steel structure problems. Highway, railway, and foot over bridges, skywalks, ramps, and cable-stayed structures. PEBs and customized fabrication. Tunnel lining formwork, with 40+ years behind it. Design, surface protection, erection, and commissioning sit under one roof.

The paperwork backs it up. RDSO vendor registration (ID 1050644) covers 10,000 MT a year, and the Alwar works has its own template, blasting and metallizing shops, with ISO 9001 from BIS. Its structural steel bridge fabrication record includes an 86 m OWG for Surat Metro and a 62 m OWG trial assembly for an ROB on the Howrah-Mumbai line.

Conclusion

So that’s the structural steel bridge fabrication procedure in India in one pass: approved drawings, a camber read cold, certified steel, a WPS held to its limits, NDT matched to stress, a checked trial assembly and 150 µm of metal spray.

When your next span is ready for the shop, send the drawings to SteelWorks.

Acronyms Used

AcronymFull form
A&CAddendum and Corrigendum
BHNBrinell Hardness Number
BISBureau of Indian Standards
DPTDye Penetrant Testing
HSFGHigh Strength Friction Grip
IRCIndian Roads Congress
IRSIndian Railway Standard
ISIndian Standard
ISOInternational Organization for Standardization
MPIMagnetic Particle Inspection
MTMetric Tonne
MTCMaterial Test Certificate
NDTNon-Destructive Testing
OWGOpen Web Girder
PEBPre-Engineered Building
QAPQuality Assurance Plan
RDSOResearch Designs and Standards Organisation
ROBRoad Over Bridge
RTRadiographic Testing
SAWSubmerged Arc Welding
SPSpecial Publication
UTUltrasonic Testing
WPSWelding Procedure Specification

FAQs

1. What is structural steel bridge fabrication?
It is the shop work that cuts, welds, tests, and coats the girders of a steel bridge before they reach the site.

2. What are the steps of steel bridge fabrication?
Structural steel bridge fabrication runs from drawings and camber layout to material checks, cutting, welding, NDT, trial assembly, metallizing, and erection.

3. Do steel bridge fabricators make their own steel?
No. Mills supply certified plates, and structural steel bridge fabrication starts once that steel clears its MTC and lab tests.

4. Which steel suits structural steel bridge fabrication in India?
Railway girders use IS 2062 E250 (quality B0 above 0°C, quality C in sub-zero areas); a road steel bridge uses the grade its design names.

5. How is a steel bridge protected from rust?
During structural steel bridge fabrication, members are shot-blasted to Sa 2½, metallized with 150 µm of sprayed aluminium, then painted.